Data Center Investment Uncertainty Raises Disclosure and D&O Risks

Published Oct 26, 2026402 readers

Shifting rules, power constraints and project delays can reshape data center economics, putting investor disclosures and board oversight under scrutiny.

Data center investment carries a governance risk that can outlast the permitting process: project assumptions may change after companies have committed substantial capital. Shifting requirements, limits on power and water, and community opposition can delay construction or reduce expected capacity. When those changes alter revenue projections, investors may question what the company disclosed and how its board monitored the investment.

That exposure is growing alongside the artificial intelligence boom. Across the United States, state and local authorities are responding to the electricity demand, environmental effects and community impacts associated with large data center projects. Companies face requirements that vary by location, and a project’s original financial case may look different by the time it becomes operational.

Local conditions are changing project economics

Recent actions show how quickly the conditions for development can shift. In July, New York temporarily paused environmental permitting for some new hyperscale data centers for up to a year while it develops a framework addressing energy costs, environmental impacts and community benefits. Pennsylvania added requirements for developers in August, including standards addressing energy affordability and environmental protection, and local approval before state permits can be issued.

Local governments elsewhere have adopted or considered limits amid concerns about electricity use, water consumption, noise and land use. Residents and environmental advocates have also opposed projects. These challenges can affect schedules and expected capacity even when a company has already announced its plans.

States associated with large data center markets are also attaching conditions to growth. Virginia adopted new site-assessment requirements for certain facilities with high energy use, and state regulators have required data centers to pay for transmission infrastructure built exclusively to serve them. Texas enacted rules for connecting large loads to its electric grid, addressing infrastructure costs and reliability. In August, Gov. Greg Abbott directed state regulators to audit data centers seeking grid connections before those projects could proceed.

The patchwork leaves developers and their corporate backers navigating different requirements across jurisdictions. With no federal regulatory scheme for data centers, the regulatory and infrastructure assumptions behind an approved project may change before operations begin. Tax incentives, permitting conditions and political opposition can also affect returns.

Changing assumptions can become securities claims

For directors and officers, the immediate exposure often centers on what investors were told. Companies may describe expected capacity, construction timing, financing needs or revenue when announcing a project. Later constraints can undercut those assumptions. If management knows that a delay, utility limitation or new requirement materially changes the outlook, earlier statements may draw scrutiny if disclosures do not reflect the new facts.

Three securities cases illustrate the range of allegations. In Masaitis v. CoreWeave, Inc., filed in the U.S. District Court for the District of New Jersey on Jan. 12, 2026, plaintiffs alleged that investors were misled about delays at a Texas data center cluster and CoreWeave’s ability to meet customer demand. CoreWeave says the allegations are meritless; the case remains in litigation. The dispute highlights how construction and capacity issues can become disclosure claims when they affect projected growth or revenue.

In Uniformed Sanitationmen’s Ass’n Compensation Accrual Fund v. Equinix, Inc., filed in the Northern District of California on Jan. 6, 2025, plaintiffs alleged, among other things, that Equinix overstated power capacity without informing investors. The federal court dismissed the power-capacity theory because the plaintiffs had not adequately alleged materiality. It allowed a separate theory concerning reported financial metrics to proceed.

Applied Digital and certain executives have also faced allegations, disclosed in the company’s 2026 Form 10-K, concerning statements about the profitability of its data center hosting business and its ability to transition to a low-cost cloud-services provider. These cases involve different allegations and procedural outcomes, but each shows how a gap between operating expectations and reported performance can draw investor claims.

Board oversight can come under scrutiny as well. Directors approving major infrastructure commitments may be asked what they knew about power prices, available water, potential changes to tax incentives and the prospect of local opposition. A board cannot anticipate every policy shift. But if an investment falters, plaintiffs may examine the information directors received, how they assessed key assumptions and whether they responded to warning signs.

Operational losses and D&O coverage are distinct

A data center’s physical performance usually does not fall within D&O insurance coverage. The management liability question arises when an operational or regulatory problem leads to allegations against directors, officers or, depending on the policy and claim, the insured company. Claims may allege misleading disclosures, deficient oversight or other governance failures.

For underwriters, exposure depends on more than the number of facilities a company owns. Geographic concentration, reliance on particular utilities or approvals, power and water needs, government incentives and board oversight of large infrastructure commitments all help describe the risk. Policy terms matter too: the insureds, covered allegations, exclusions and other provisions determine how a particular claim may be handled.

Connect project reporting to investor disclosures

Risk managers can help boards track data center uncertainty as a business risk rather than treating it solely as a permitting matter. Regular reporting on major projects can cover regulatory developments, utility capacity, water access, community opposition, construction progress, financing, tax incentives and changes to projected economics. Companies also need clear escalation processes when core assumptions shift materially.

Disclosure controls should draw on current information from the teams closest to the work. Statements about completion dates, expected capacity, costs and revenue are more reliable when those preparing public disclosures have updates from construction, utility, permitting and regulatory teams. The aim is to spot a widening gap between what a company expects and what a project can deliver while there is still time to reassess the message.

Insurance reviews also benefit from happening before a public announcement or capital commitment. Risk managers and brokers can trace plausible loss scenarios through the insurance program, identify which policies might respond and check for provisions that could leave gaps. That review can help align coverage expectations with the company’s actual project risks.

The central exposure isn’t that every data center will face a pause, lawsuit or cost overrun. It’s that investment commitments are large while assumptions about approvals, infrastructure and operating capacity can change. Boards that keep those assumptions visible—and connect project updates to public disclosures—will be better positioned to explain how expected returns have shifted.

Patrick M. Kennell is co-managing partner of Kaufman Dolowich’s New York office. Kristen S. Swift is managing partner of the firm’s Delaware office. Both defend directors, officers and corporations, and handle insurance coverage matters.

Source: Patrick M. Kennell and Kristen S. Swift · www.businessinsurance.com